siding begins
we have some hardie panels installed. boards are installed with 1/2" open joint over 2x4s laying flat.
Sunday, September 27, 2009
drywall
Friday, September 25, 2009
insulation and drywall
all ceilings and walls are insulated with batts in addition to 2" layer of foam. this assembly should result in R32 walls and R52 ceilings. we still need to insulate foundation concrete. for this purpose we will use 1 1/2" extruded polystyrene boards, same as we used for underslab insulation.
drywall hanging started today. it goes really fast, but the whole process needs to be coordinated with soffit framing . droped soffit in living room will give it a better height to width proportion.
drywall hanging started today. it goes really fast, but the whole process needs to be coordinated with soffit framing . droped soffit in living room will give it a better height to width proportion.
Saturday, September 19, 2009
spray foam and siding wood
half of the house is now sprayed with foam insulation. it is closed cell foam with R-7 per 1". we are doing 2" walls and roof and combine it with batts, as this stuff is quite expensive. it does seal and laminate the whole house envelope, making it air tight and structurally stronger.
also our siding hardwood was delivered today. ultimately we decided for brasilian mahagony which we will treat with Penofin Hardwood stain.
also our siding hardwood was delivered today. ultimately we decided for brasilian mahagony which we will treat with Penofin Hardwood stain.
Friday, September 18, 2009
trip to ikea
we took trip to Ikea in Salt Lake City. This is the closest store to denver. We flew there and drove back. Phone ordered our kitchen cabinets and appliances to make sure we will get everything we need. Ouro rder was delivered to storage warehouse where we picked it up. In addition we bought what we liked in actuall Ikea store.
and some images from our drive back.
and some images from our drive back.
Tuesday, September 15, 2009
hardi framing
Sunday, September 13, 2009
rosin paper
our mechanical room, still empty, once it gets filled with all the equipement, there will be hardly any space in it.
our contractor asked us to cover floors since closed cell spray foam insulation will be blown in this upcoming week. we used rosin paper, which we will keep over floor until painting is complete. whole place looks like it got "beautifull" pink carpet. also while jana was covering floors, i installed blockings in exterior wall cavity for siding attachement.
our contractor asked us to cover floors since closed cell spray foam insulation will be blown in this upcoming week. we used rosin paper, which we will keep over floor until painting is complete. whole place looks like it got "beautifull" pink carpet. also while jana was covering floors, i installed blockings in exterior wall cavity for siding attachement.
Saturday, September 12, 2009
Sunday, September 6, 2009
Friday, September 4, 2009
windows
windows are finally here. after receiving quotes on windows that ranged anywhere between $5000 adn $72000, we decided to go with Jeld Wen Siteline EX serie, with extruded aluminum exterior and wood interior. Even though it is not exactly the look we wanted (which was totally out of our budget), they are very decent quality for the price.
in one day, all the windows were installed. we are still waiting on patio double sliding door.
meanhile we started to collect all the tools we might need for the work we are planing to do ourselves.
in one day, all the windows were installed. we are still waiting on patio double sliding door.
meanhile we started to collect all the tools we might need for the work we are planing to do ourselves.