Sunday, October 11, 2009

weekend progress

we assembled all kitchen cabinets this saturday. doors and drawers will be installed later, after cabinets are in place and countertop is in place. our friend tomas helped us to manage this in one day.
sunday we finished installing and painting rain screen supports. as a final touch i rented planer and shaved verticals that were not in plane with other ones, to ensure that siding lines will be straight.

Thursday, October 8, 2009

Monday, October 5, 2009

tiling

tiling master shower.



aluminum channel at wall base meeting door frame. frame will be painted and connection with drywall caulked.
guest bath tile for shower enclosure. in real, the color is completely different.



Friday, October 2, 2009

progress images

today i poured second concrete shower pan in guest bath. the plan is to seal concrete with couple layers of sealer, and have mahagony wood slats as shower floor.